FLS South Nasr City:

By the end of 2013 CIRA is planning to complete the building of FLS at South Nasr City on land area of 8400m^2 and building area of 10500m^2. 
The school will include education levels from nursery to high school .The expected cost is 18 million pounds.

 

Location
South of Nasr city
Student capacity
1973
Enrollment
K-12

 



FLS Asuit:

upper Egypt for educational services (A CIRA subsidiary) had  completed the building of FLS at Asuit on land area 12700m^2 and building area of 10954m^2. The school included education levels from nursery to high school .The expected cost is 15 million pounds. 

 

Location
Asuit residential area
Student capacity
1512
Enrollment
K-12

 

 

 

 

FLS Menya:

By the end of 2013 upper Egypt for educational services (A CIRA subsidiary) is planning to complete the building of FLS at Menya on land area of 10287m^2 and building area of 7351m^2. The school will include education levels from nursery to high school with expected cost 10 million pounds.



Location
Menya residential area universities district- Menya
Student capacity
1092
Enrollment
K-12

 

 



FLS Alexandria:

By the end of 2014 Alexandria for educational services (A CIRA subsidiary) is planning to complete the building of FLS at Alexandria on land area of 23000 m^2 and building area of 17644m^2 for the language school and 12851 m^2   . The school will include education levels from nursery to high school with  expected cost 23 million pounds.

 

Location
Alex west (Alexandria)
Student capacity
1960
Enrollment
K-12

 

 

 



 

Badr University:

CIRA owns Badr University in Badr City that of total area  45 acres  that includes three phases ,
Phase 1  includes 3 colleges pharmacy and pharmaceutical industries ,dentistry ,and business,,Finance and Economics in addition to the management building Badr University also include 2 other  phases ,
Phase 2 include colleges physical therapy, Foreign Languages and translation , and Cinematic and theatrical Sciences .
Phase 3 include colleges Fine arts ,Engineering and technology also include Mosque and   residence building.
By the end of   2014 CIRA is planning to open phase 1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 